The project involved relocating (E) chiller and adding five (5) new chillers without disrupting to support of the occupied and operating outpatient Imaging Center with shutdowns and crane picks scheduled for off-hours.
We expanded the size of the chiller yard, custom perforated panels and louvers, new electrical distribution, and process piping to support MRIs and CT machines. Project footprint and construction activities were laid out and sequenced to minimize disruption to traffic and the loading dock. Clinical disruptions were kept to a minimum by conducting commissioning during off-hours when patient loads were low.